Performance Park Bridge

About The Project

This bridge crosses Fall River directly south of the Performance Park Amphitheater. It is believed to have been built in the 1960's. During the summer of 2024, rotation and displacement of the north abutment from river scour was observed and the bridge was closed to vehicular traffic. Additional movement was observed in the spring of 2025 and the bridge was closed to all traffic. 

In June 2025, maintenance staff from the Town of Estes Park Public Works Street and Stormwater Division teamed with a private contractor to remove the bridge deck. This demolition work was a preemptive effort to avert a potential blockage and flood overflow in the river if the bridge were to collapse. 

Design efforts for a replacement bridge will commence in 2025 in preparation for construction of a new bridge, tentatively in 2026. All work is part of the new stormwater management program funded in part by the one percent sales tax approved by voters under the 2014 Ballot Issue 1A.

For more information, contact Greg Muhonen, Project Manager, at 970-577-3581 or gmuhonen@estes.org.

Performance Park Bridge

Project Schedule

  • June 2025: Existing bridge removed
  • July 2025: Request for Proposals released
  • August 2025: Design-build bids due
  • September 2025: Contract award by Town Board
  • October 2025 through March 2026: River modeling and bridge design
  • April 2026 through May 2026: Bridge construction
Performance Park Bridge Removal

September 2025

Contract award consideration by Town Board.

August 2025

Two bids received. Apparent low bidder is High Plains Excavation and Aggregate.

July 2025

Invitation to Bid published.

June 2025

Existing bridge deck removed.