Reclamation Neighborhood Water Improvements Project

Overview

The Water Division and Public Works Department have jointly completed the design for improvements in the Reclamation Neighborhood. This project includes replacing the existing 4-inch water mains located behind homes with new 8-inch ductile iron mains located in the road. Service lines will be reconnected to the water system with construction work required on most properties. Street and sidewalk improvements will be made on Third Street, North Court, and South Court. For more information on the street and sidewalk improvements please visit the Public Works Reclamation Neighborhood Street Improvements page.

For more information and updates on this project, please contact Jacqui Wesley, Utilities Project Manager at 970-577-3611 (jwesley@estes.org) or Mike Dantimo, Capital Projects Supervisor at 720-333-7152 (mdantimo@estes.org).

About This Project

Wagner Construction has started work in the Reclamation Neighborhood. Construction will continue through November 2024. After a break during the winter months, construction will resume in Spring 2025. Final completion is expected to be in May/ June 2025.

Work will start along Third Street, North Court and South Court first, then proceed along U.S.36 (Summer 2024). The final piece of construction will be First Street followed by Second Street, anticipated to start in September 2024. New asphalt pavement, wider sidewalks and new curb and gutter will be installed on Third Street, North Court and South Court detour and road closure information will be posted throughout the construction area. You can find a map of the project area below.

For more information on the water portions of this project, please contact Jacqui Wesley, Utilities Project Manager at 970-577-3611 (jwesley@estes.org) or Mike Dantimo, Capital Projects Supervisor at 720-333-7152 (mdantimo@estes.org). For information on paving, sidewalks, or drainage, please contact Trevor Wittwer with Public Works at 970-577-3724 (twittwer@estes.org).

Project Information and Updates

Reclamation Neighborhood Drawings

3 Week Schedule (October 7, 2024 - October 25, 2024)

Project Update Map

Wagner Construction is nearing completion of the work in the Reclamation Neighborhood. All water service lines have been connected to the new water system and the old water system is no longer connected to any water source. Street construction will continue into Spring 2025 along 3rd Street, South Court, and North Court to finalize paving, curb, gutter and sidewalk replacements. Please watch for continued traffic pattern changes and detours in place on these streets. Work on the other street is complete except for some restoration and seeding. Final completion for all work is expected to be in May/June 2025.

During project construction, the Xcel Energy gas services lines were found to be too shallow. Xcel Energy hired a contractor to lower many of the lines in this area to meet their standards for depth of bury. This work was done by Xcel as a separate concurrent project. Now that the water work is complete, Estes Park Sanitation District can start a planned sewer system rehabilitation project.

Project History

The Town and Wagner Construction hosted a public meeting on June 6, 2024 at the Estes Park Museum. The presentation material is available online. The information in this presentation, including the schedule, is subject to change. For the most up-to-date schedule, please see the schedule linked above on this web page.

The project went out to bid on March 15, 2024. Bids closed on April 11, 2024. Wagner Construction was awarded the project.